This week plans
I'd like to tie up the flumotion components this week(by Tuesday or Wednesday) and get started on the build system. I need to do a little bit of testing on getting the components connected and make sure that's all working well.
Snippets for today
- Worked on getting sshd running and configured properly with public key auth on the flumotion(encoder/collector) hosts so that pushconfigs.py will work.
- Public keys for auth will need to be placed in sources/public_keys and the docker image will need to be built each time the public keys change, but I think this is the correct way to handle this given that the addition doesn't require extensive additional building
- Did some reading on setting up Vagrant for the next part of the project
- Drove back to SB from home, and did some moving into my new place!